pm-gantt-chart
ASCII Gantt chart renderer for pm-cli
安装
已安装 pm 时
pm install npm:pm-gantt-chart --project使用 npm,无需安装 pm
npx -y @unbrained/pm-cli install npm:pm-gantt-chart --project使用 Bun,无需安装 pm
bunx @unbrained/pm-cli install npm:pm-gantt-chart --projectREADME
Gantt chart renderer for pm-cli with ASCII, SVG, HTML and Mermaid exports, dependency-aware scheduling and Triplicate styling.
Renders your pm items as a week-by-week timeline in the terminal — grouped by milestone, sprint, release, assignee, status, type, or tag — and exports the same chart to Mermaid gantt, standalone HTML, ASCII, a CSV schedule, or structured JSON. Can compute and highlight the critical path (longest dependency chain), and run dependency-aware scheduling that derives each item's start/end from its blocked-by chain plus estimates.
Example output
pm gantt • 8 weeks from 2026-06-01 • critical path marked
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
GROUP ITEM S W1 W2 W3 W4 W5 W6 W7 W8
──────────────────────────────────────────────────────────────────────────────────────────
Jun 1 Jun 8 Jun 15 Jun 22 Jun 29 Jul 6 Jul 13 Jul 20
──────────────────────────────────────────────────────────────────────────────────────────
S1 *Build endpoint ▶ ▓▓ ▓▓
*Design API ✓ ▓▓
S2 *Release ○ ▓▓ ▓▓ ▓▓ ▓▓
Write docs ○ ░░ ░░ ░░
*Integration tests ○ ▓▓ ▓▓ ▓▓
(no milestone) Backlog grooming ○ ░░ ░░
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
Legend: ██ in_progress/blocked ░░ open/planned ▓▓ critical-path (*) ·· undated S: ▶in_progress !blocked ✓closed ○open
Installation
Requires pm CLI 2026.10.20 or newer for locked scenario-selection guards.
Development and CI use the exact SDK pin declared in package.json;
the consumer floor is independently exercised by packed npm acceptance.
In a plain project directory, initialize a tracker and activate the published package:
npx -y @unbrained/[email protected] init --defaults --agent-guidance skip
npx -y @unbrained/[email protected] install npm:[email protected] --project
With Bun:
bunx @unbrained/[email protected] init --defaults --agent-guidance skip
bunx @unbrained/[email protected] install npm:[email protected] --project
Use the explicit npm: source: an owner/repository shorthand is interpreted as a
local path, not as a registry package.
Without git
Rendering, scheduling and chart exports work with a plain-directory tracker; no git repository or git executable is required. GitHub sync and changelog commands based on tags need a git repository and their separate tools.
Usage
Terminal chart — pm gantt
# Default: 8 weeks, grouped by milestone, all statuses
pm gantt
# Show 12 weeks
pm gantt --weeks 12
# Group by sprint / release / assignee / status / type
pm gantt --group-by sprint
pm gantt --group-by release
pm gantt --group-by assignee
pm gantt --group-by status
# Show only in-progress items
pm gantt --status in_progress
# Anchor the window at a specific date, or clip it with --to
pm gantt --from 2026-06-01 --weeks 16
pm gantt --from 2026-06-01 --to 2026-08-01
# Dependency-aware scheduling: derive start/end from blocked-by chains + estimates
pm gantt --schedule
pm gantt --schedule --default-duration 3
# Compute & mark the longest dependency chain
pm gantt --critical-path
# Show only the critical path (great paired with --schedule)
pm gantt --critical-only --schedule
# Show each item's % complete on its bar
pm gantt --progress
# (or use the --show-progress alias)
pm gantt --show-progress
# Overlay fixed release/deadline dates as labeled vertical markers
pm gantt --milestones "v1.0=2026-06-30,v1.1=2026-08-15"
Export — pm gantt export
# Mermaid `gantt` diagram (default format) to stdout. Use the global --quiet
# flag when piping so the CLI's command receipt is not appended to the artifact.
pm --quiet gantt export
# Mermaid to a file
pm gantt export --format mermaid --output roadmap.mmd
# Standalone, self-contained HTML
pm gantt export --format html --output roadmap.html
# Scalable Vector Graphic (SVG) — a self-contained vector render of the chart.
# Use --width to request the canvas width in pixels (default 1000, clamped 320..8192).
pm gantt export --format svg --width 1600 --output roadmap.svg
# Plain ASCII (the same chart `pm gantt` prints)
pm gantt export --format ascii --output roadmap.txt
# CSV schedule: id,title,start,end,duration_days,slack_days,deps,status,critical,progress_percent,overdue,off_window
pm gantt export --format csv --schedule --output schedule.csv
# Structured JSON schedule for agents / programmatic consumers
pm gantt export --format json --schedule --output schedule.json
# Export honors the same shaping flags (including --schedule / --critical-only)
pm gantt export --format html --group-by assignee --critical-path --weeks 12 --output team.html
pm gantt export --format mermaid --schedule --group-by sprint --output plan.mmd
The exporter writes to the file given by --output, or prints to stdout when omitted. For a clean pipe or redirect, invoke it as pm --quiet gantt export …; --quiet suppresses the CLI's trailing command receipt while retaining the exported artifact.
Options
Both pm gantt and pm gantt export accept the shaping flags:
| Flag | Values | Default | Description |
|---|---|---|---|
--weeks <n> |
1–52 | 8 |
Number of weeks to display (ignored when --to is set) |
--group-by <field> |
milestone | sprint | release | type | assignee | status | tag |
milestone |
How to group items into rows |
--status <filter> |
open | in_progress | blocked | closed | canceled | draft | all |
all |
Filter items by status |
--from <iso> |
YYYY-MM-DD |
current week | Anchor the chart window at this date |
--to <iso> |
YYYY-MM-DD |
— | Clip the window to end at this date (derives the week count, overriding --weeks) |
--schedule |
flag | off | Dependency-aware scheduling: derive start/end from blocked-by chains + estimates |
--default-duration <days> |
integer ≥ 1 | 5 |
Fallback duration for items with no estimate under --schedule |
--critical-path |
flag | off | Compute & mark the longest dependency chain |
--critical-only |
flag | off | Show only items on the critical path (implies critical-path computation) |
--progress |
flag | off | Show each item's % complete on its bar |
--show-progress |
flag | off | Alias for --progress — show each item's % complete on its bar |
--width <px> |
integer ≥ 1 | 1000 |
Requested render width in pixels for SVG and HTML (clamped 320..8192; SVG expands when needed to preserve readable week columns; ignored by ASCII/Mermaid/CSV/JSON) |
--milestones <list> |
name=YYYY-MM-DD,… |
— | Draw fixed release/deadline dates as labeled vertical markers on the timeline |
pm gantt export adds:
| Flag | Values | Default | Description |
|---|---|---|---|
--format <fmt> |
mermaid | html | svg | ascii | csv | json |
mermaid |
Output format |
--output <file> |
path | stdout | File to write (prints to stdout if omitted) |
json emits the computed schedule as structured, machine-readable data — window, options, a summary (project span, critical-path length, total task-days, per-group workload), milestones, and an items[] array where each entry carries id, title, type, status, group, ISO start/end, durationDays, slackDays, progress, critical, overdue, infeasible, offWindow, and gating deps. Unlike pm --json gantt (which returns the rendered ASCII chart plus summary counts), this is the full per-item plan, so agents and scripts can reason about the schedule without parsing a chart or CSV. Output is deterministic (no embedded wall-clock), so identical input produces byte-identical JSON. Pair with --schedule for dependency-derived dates and slack.
csv emits a schedule table: id,title,start,end,duration_days,slack_days,deps,status,critical,progress_percent,overdue,off_window (deps = space-separated blocking ids). Pair it with --schedule for dependency-derived dates and slack. slack_days is the total float in days (only populated under --schedule; blank otherwise): 0 marks a critical-path item, a positive value is how many days the task can slip without delaying the project, and a negative value means the plan is already late for a downstream deadline. The trailing risk columns make the CSV useful directly in spreadsheets and portfolio reports: critical/overdue are yes/no, progress_percent is 0..100, and off_window distinguishes before, after, and undated rows.
svg emits a self-contained, scalable vector graphic of the chart — the same grouped rows, week columns, status-colored bars, critical-path highlighting, overdue markers, off-window hints, today rule, milestone diamonds, and --progress fill as the HTML render, but as resolution-independent SVG primitives. Use --width to request the canvas width in pixels (default 1000, clamped to 320..8192). For long timelines the SVG expands beyond that request rather than clipping the chart, preserving a readable 24px minimum per week. The output is a single <svg> document (with an <?xml?> prologue) suitable for embedding in docs, slides, or websites, or for rendering at any zoom level without pixelation.
Slack / float, critical path & infeasible deadlines
Under --schedule, a backward pass (classic CPM) computes each item's latest feasible start/finish from the project end and any downstream deadlines, then derives total slack = latest start − earliest start:
- 0 slack → the item is on the critical path; any slip delays the project.
- positive slack → the item can slip that many days harmlessly.
- negative slack → the item's required start (to hit a downstream deadline) is before its earliest feasible start. The plan is already late. These items are listed in a
WARNING:block on stderr by bothpm ganttandpm gantt export, and flagged per-task in the JSON result (tasks[].slack_days,tasks[].infeasible, plusinfeasibleCount/warnings).
Minimal deadline repair proposals
pm gantt repair evaluates explicit changes for a fixed deadline. It returns the
fewest moves that make every retained active item feasible under the existing
forward/backward scheduler, including each item's own deadline. Repair feasibility
uses earliest starts rather than the chart's just-in-time deadline placement:
waiting until a later deadline must not create a need for extra capacity.
Closed/canceled prerequisites count as satisfied. It never writes items, estimates, deadlines,
dependencies, or plan decisions.
pm gantt repair --from 2026-10-21 --deadline 2026-10-22 \
--capacity task-a=960 --defer task-b --forbid task-release --json
Only named offers are considered: --capacity id=minutesPerDay,... supplies
dedicated daily capacity for estimated work (baseline 480 minutes/day; offers
481..4800), and --defer id,... allows those exact items to leave this scenario.
No retained item may depend on deferred work. --forbid id,... overrides both.
Capacity availability is a caller-supplied assumption; this is a precedence and
calendar-day model, without shared-resource contention, weekends, or holidays.
Output uses the host's compact TOON by default or JSON with --json. Each
proposal includes exact moves, affectedIds (moved items plus items whose dates
change), recomputed finish/retainedCount, deferredMinutes, and
addedMinutesPerDay. Titles, bodies and full schedules are omitted.
minimalChanges is minimum move count within the explicit vocabulary;
ties prefer less deferred effort, then less added daily capacity, then stable
move order. totalProposals and truncated describe output limiting.
Bounds: 200 corpus items, 2000 ordering edges, 24 effective offers, 1..3 moves
(--max-changes, default 3), 1..10 results (--max-proposals, default 5), and
1..10000 evaluations (--max-evaluations, default 5000). Missing estimates use
--default-duration (default 5 calendar days, 1..365); they cannot receive a
capacity offer. Estimates must be zero or finite values from one second (1/60 minute) through 175200 minutes.
Cycles, missing prerequisites, malformed dates, invalid offers, oversized
scenarios, exhausted search and unavailable repairs return typed refusals with
code, message, remedy (CLI exit 2). Search exhaustion never presents an
uncertified minimum. An already feasible scenario returns zero changes and no
proposals. Full ISO tracker deadlines are accepted; CLI scenario days require
real YYYY-MM-DD values.
The typed SDK exports proposeDeadlineRepairs(items, options, graph?) and
DeadlineRepairOptions, DeadlineRepairResult, DeadlineRepairProposal,
DeadlineRepairMove, DeadlineCapacityShift, DeadlineRepairRefusalCode.
Pass a complete dependency-closed corpus. The optional graph uses the existing
PrerequisiteGraph contract for custom registry ordering; the CLI resolves
workspace registrations automatically. Core plan decision can record a chosen
proposal after review. See the worked example.
Without git
Rendering, scheduling, exports, duration calibration, uncertainty intervals and deadline repair proposals work in plain trackers without git installed. This package's runtime commands do not require a git repository. Repository release/changelog tooling needs git history.
Forecast and calibration APIs share one strict duration input contract.
Malformed estimates, sampling controls, calibration controls and native effort
fields return invalid_estimate with remedies before numerical work. Sparse
arrays, nonfinite numbers, negative zero, invalid dates and extra keys in closed
objects are refused.
Successful calibration and forecast results pass a numeric/date output contract
before SDK return or CLI serialization. Invalid computed fields return
invalid_estimate naming the field; ratios are never emitted as Infinity or null.
See the documented domain and output ranges.
Observed-duration calibration
pm gantt calibrate --type Task --minimum-samples 10 --json compares elapsed
calendar minutes with planned effort at verified start, for an exact task class
and optional --tag. Default output is compact TOON. Canceled, reopened,
incomplete and unverifiable histories are disclosed; too few usable episodes
returns a typed refusal with remedies and no numerical calibration.
The typed SDK calibrateObservedDurations(pmRoot, options) returns deterministic
nearest-rank quantiles, complete sample counts, bounded diagnostics and an
explicit {kind: "empirical", values: [...]} duration population. Callers can
choose to pass it to completionIntervals with minutesPerDay: 1440 for calendar
time. Estimates stay unchanged; elapsed time includes waits and makes no causal
productivity claim. See the worked SDK/CLI example and evidence rules.
Schedule drift explanations
pm gantt snapshot --scenarios resources.json --json > before.json saves one
explicit resource alternative. Capture a second snapshot after reviewed changes,
then run pm gantt drift --before before.json --after after.json --limit 20
(append --json for JSON; default TOON). The existing resource engine replays
estimates, calendars, shared owner capacity and prerequisites. Each moved goal
has its exact civil-day delta, individual counterfactual witnesses and causal
routes; unchanged finishes collapse to snapshot/id references. Missing inputs,
unknown status roles and unsupported changes remain gaps with remedies.
Complete saved snapshots replay through a 16 MiB file transport, with a shared
4 MiB canonical JSON budget enforced by capture and validation. Calendar names
including constructor and __proto__ remain ordinary own entries.
SDK: captureScheduleScenario, validateScheduleSnapshot,
explainScheduleDrift and exported snapshot/result types. These operations are
read-only and work without git. See the worked example and limits
and public tracker measurements.
Resource-constrained schedule scenarios
pm gantt resources --scenarios resources.json compares explicitly named
alternatives with shared assignee capacity, weekday/holiday calendars and daily,
weekly and total minute limits. It returns bounded TOON (default) or --json,
per-item computed dates, numerical owner overload witnesses, counts and revision
receipts. Existing item dates stay unchanged. Calendar days use an explicit IANA
time zone and reproduce across host zones and daylight-saving weekends.
Explicit --select, --selection, --expect-revision, --target and
--target-revision record a feasible reviewed snapshot as a core note through
the SDK's journaled mutation and locked target revision check. Source changes
require recomputation. The allocator is a deterministic heuristic; exhaustion
without a capacity witness does not prove global infeasibility. Missing effort
or capacity refuses with a typed remedy. The typed SDK exports
resourceScenarios, applyResourceSelection and their calendar, alternative,
result, refusal and selection types. Everything works without git. See the
worked example, bounds and selection semantics.
Effort and external waiting
pm gantt waiting --waits waits.json previews declared external waits separately
from native estimated effort. Default output is compact TOON; append --json
for JSON. A task with 120 minutes of effort and a 2880-minute external wait
consumes 120 capacity minutes and spans 3000 elapsed minutes in the
continuous-minute model. Previews preserve ownership, claims and all native data.
{"waits":{"project-task":{"minMinutes":2880,"maxMinutes":2880}},"limit":20}
Bounds omitted inside a declared wait stay null (unknown), including downstream
completion bounds. An absent declaration means zero declared wait, not evidence
that a task has no real-world delays. Counts and total effort cover the complete
scope; limit bounds only returned rows. Configured SDK status roles and ordering
relationships govern the projection. Use pm next for core readiness and
gantt resources for shared owner calendars/capacity. This preview models one
serial wait after effort, with unlimited parallel effort and elapsed minute
offsets; it does not forecast calendar dates or manage reservations/reminders.
The typed SDK exports effortWaitingPreview for an already certified corpus and
previewEffortWaiting for a fresh SDK read. Both use the same strict boundary and
finite output contract. See the worked SDK/CLI example and refusal remedies.
Completion intervals for agent plans
pm gantt uncertainty samples declared effort uncertainty over the existing
registry-aware prerequisite graph. Pass a JSON map of active item ids to bounded
minute ranges ([480,2400]), uniform distributions
({"kind":"uniform","min":480,"max":2400}), triangular distributions
({"kind":"triangular","min":480,"mode":960,"max":2400}), or fixed points
({"kind":"point","minutes":960}). Unchanged recorded estimates are fixed
points; missing estimates and every dependent completion remain unknown.
pm gantt uncertainty --from 2026-10-22 --seed 42 --estimates estimates.json
pm gantt uncertainty --from 2026-10-22 --seed 42 --estimates estimates.json --json
Compact TOON (default) and JSON include project/per-item completion quantiles,
unknown counts, a sensitivity ranking and a complete scenario receipt. Defaults
are 2000 samples, probabilities 0.1/0.5/0.9, 480 effort minutes per calendar day
and 20 output rows. Override with --samples, --quantiles,
--minutes-per-day, and --limit. Quantile finishes are exclusive UTC instants;
continuous durations do not round up to whole days like the bar renderer.
Independent effort draws, unlimited parallel capacity and no holidays/resource
contention are explicit assumptions. Deadlines and creation dates do not postpone
earliest starts. This evaluates declared uncertainty and trains no model.
The receipt retains the algorithm version, unsigned 32-bit seed, resolved inputs,
normalized dependencies, controls, assumptions and SHA-256 input hash. Output
limits bound item/sensitivity rows while retaining all receipt inputs; counts
and truncated expose omissions. An unknown project finish suppresses project
quantiles and sensitivity. Otherwise dominantEstimate identifies the largest
absolute Pearson correlation between a sampled estimate and project finish.
This is linear association, not causal variance attribution; constants return
zero correlation. Monte Carlo quantiles and sensitivity are approximate.
Bounds: 200 corpus items, 2000 ordering edges, 100..10000 samples, at most
5,000,000 sample × (item + edge) operations, 1..200 output rows and 1..9 strictly
increasing probabilities in [0,1]. Effort is finite, ordered and within
zero or 1/60..175200 minutes; effort per day is 1..1440. --estimates must be a regular JSON
object file no larger than 64 KiB. Cycles, missing prerequisites, invalid inputs
and exceeded bounds return typed code, message, remedy refusals (exit 2).
The command does not mutate tracker documents or write the receipt implicitly.
The typed SDK exports completionIntervals(items, options, graph?),
CompletionIntervalOptions, CompletionIntervalResult, UncertainEstimate,
CompletionScenarioReceipt and related quantile/refusal types. It reuses the
SDK execution kernel and the package's registry-aware graph adapter. Supply a
complete dependency-closed corpus; the CLI certifies its full read and resolves
custom workspace ordering automatically. See the worked example and receipt
replay.
Preflight data-sanity gate
Before rendering, both pm gantt and pm gantt export run a preflight data-sanity gate so bad data surfaces early instead of producing a silently-confusing chart. It splits problems into two tiers:
Hard-fail (blocks, non-zero exit) — a dependency cycle. A cycle has no valid topological order, so dependency-aware scheduling is impossible and any chart drawn from it would be plausible-looking but wrong. The command aborts with a clear error naming the full cycle path, e.g.:
gantt: 1 fatal data problem(s) make scheduling impossible: • dependency cycle: pm-a "Design" → pm-b "Build" → pm-a "Design" Resolve the dependency cycle(s) above and re-run.Warn (non-blocking, stderr; chart still renders, exit 0) — soft issues that still yield a useful chart: a deadline that precedes the item's own start date, and an implausibly large estimate (over ~2000h, almost always a minutes-vs-hours unit error). These print a
NOTE:block on stderr and are suppressed under--jsonto keep machine-readable output clean.
Fully valid data produces no warnings and no block. (Infeasible/unreachable downstream deadlines are a separate, lighter signal — they are flagged in the schedule's backward pass rather than by this gate; see above.)
TODAY marker (all formats)
The current week is indicated in every format, shown only when "today" falls inside the chart window:
- ASCII — a
▼TODAYcaret under the week column that contains the current date. - Mermaid — a
%% today: <date>comment. - HTML — the matching week column is highlighted with a red vertical rule and a
▼ todaylabel in the header.
--milestones — fixed release/deadline dates
Items are scheduled work; milestones are immovable calendar targets (a release, a launch, a contractual deadline). In cross-functional views that aren't grouped by milestone, those dates are otherwise invisible. --milestones overlays them as labeled vertical markers so deadline pressure is obvious at a glance.
Pass a comma-separated list of name=YYYY-MM-DD entries:
pm gantt --milestones "v1.0=2026-06-30,v1.1=2026-08-15"
- ASCII — a
▼<name>caret in the week column the milestone lands in (parity with the▼TODAYmarker). Multiple milestones in the same week are comma-joined (▼v1.0,beta). - Mermaid — a dedicated
section Milestoneswith native zero-duration:milestonemarkers on the exact date, so they render as the diamond marker. - CSV — appended rows (
id=milestone:<name>,status=milestone,start=end=date) so the dates round-trip alongside the schedule.
Milestones outside the rendered window are ignored on the chart/Mermaid output, with a one-line note on stderr (CSV still includes them so the data round-trips). Malformed entries (missing =, empty name, or a non-ISO date) fail cleanly with a usage error rather than crashing. The same flag is honored by pm gantt export.
--progress — % complete on bars
--progress (opt-in) renders each item's completion ratio on its bar. The ratio is derived deterministically from available pm signals:
- closed / canceled → 100%
- an explicit
meta.progress/meta.percent_completenumber (a0..1fraction or a0..100percent) → honored verbatim - an acceptance-criteria checklist in the body (
- [x]vs- [ ]) → checked / total - in_progress with no other signal → 50% (a "halfway" default); blocked → 25%
- everything else (open / draft) → 0%
It surfaces as a trailing NN% plus a coarse fill glyph in ASCII (·· 0% · ░░ 25% · ▓░ 50% · ▓▓ 75% · ██ 100%), as a %% tN progress: comment in Mermaid (the diagram has no native per-task percent field), as a width-sized fill overlay plus a NN% label in HTML, and as progress_percent in CSV.
Overdue / deadline-risk highlighting
Items whose deadline is before today and that are not closed/canceled are flagged automatically (no flag needed):
- ASCII — a trailing
‼ OVERDUEmarker on the row. - Mermaid — the task carries the
crittag (the diagram's deadline-risk styling) plus an%% overdue:comment. - HTML — the bar gets a red striped fill, the due date turns red, and the row label shows a
‼ overduemarker.
Overdue items are also counted in the JSON result (overdueCount, overdue[]) and listed in a NOTE: block on stderr (suppressed under --json).
Off-window vs. undated items
A genuinely undated item (no dates at all) and an item whose dates fall entirely outside the chart window used to look identical (both ··). They are now distinguished:
- undated →
··(ASCII) / a hatched cell (HTML). - off-window earlier →
←·(ASCII) / a←hint in the first column (HTML). - off-window later →
·→(ASCII) / a→hint in the last column (HTML).
The JSON result reports offWindowCount and undatedCount. Mermaid is unaffected (it always renders real dates).
ASCII TODAY marker
The terminal chart draws a ▼TODAY caret under the week column that contains the current date (parity with the Mermaid %% today: marker and the HTML today column), shown only when "today" falls inside the chart window.
HTML summary & assignee workload
The HTML export ends with a Summary footer — project span (start → end and day count), critical-path length, and total task-days. When exported with --group-by assignee, an additional Assignee workload table lists each assignee's total task-days (descending).
How it works
- Columns — each column is one calendar week, starting from the Monday of the anchor week (
--from, or the current week by default).--toclips the window and derives the week count. - Rows — items are grouped by the chosen field; items with no value land in a
(no milestone)/(no sprint)/(no release)/(no type)/(unassigned)/(no tag)group.--group-by statusgroups by lifecycle status. - Bars (default) — a bar spans from the item's
created_atto itsdeadline. If only a deadline is known, a one-week bar ending on it is shown. Items with no dates at all are shown as··(undated). - Bars (
--schedule) — a forward pass schedules each item after its registry-defined prerequisites finish.A blocks BandB blocked_by Aboth put A before B; equivalent inverse rows are deduplicated. Active extension kinds use their declared ordering and precedence. Association, implementation, provenance, temporal, and unknown kinds remain context without ordering work. Duration comes fromestimated_minutes(8h workday, rounded up to whole days) or--default-duration. Items with a reachabledeadlineare back-anchored to end on it. The chain ordering, not the calendar, drives the bars — a late chain can push a dependent past its deadline, which is exactly what a schedule should expose. - Critical path — with
--critical-path(or--critical-only), the longest chain ofdependenciesedges is computed (cycle-safe), its items prefixed with*and drawn with▓▓bars. Ties break toward the chain with the latest final deadline.--critical-onlydrops every off-path item. - Symbols —
██= in_progress/blocked,░░= open/planned,▓▓= critical path,··= undated,←·/·→= off-window (dates earlier / later than the window),‼ OVERDUE= past deadline & not closed.
Item fields used
Items are read via canonical pm list --all --json with bodies, strict source
reads, full projection, no truncation, and both universal output bounds set to
unbounded. The public pm SDK certifies source, filter, pagination,
projection, count, and identity receipts; pm-gantt-chart adds narrow
fail-closed checks for unreadable counters and omission/read-output evidence
not yet covered by SDK 2026.8.21. A partial or unverifiable workspace read
exits non-zero instead of drawing a plausible-looking chart with missing work.
| Field | Used for |
|---|---|
title |
Row label |
status |
Bar style and status symbol; also used with --status filter |
deadline (or legacy due_date) |
Right edge of the bar; back-anchor target under --schedule |
created_at |
Left edge of the bar (default mode) |
estimated_minutes |
Task duration under --schedule (8h workday) |
sprint / release / milestone |
Group key for --group-by milestone (default), sprint, release |
type |
Group key for --group-by type |
assignee |
Group key for --group-by assignee |
status |
Group key for --group-by status; also bar style |
tags[0] |
Group key for --group-by tag |
dependencies[].id (registry ordering: true) |
Normalized prerequisites used for scheduling, cycles, critical path, slack, and CSV/JSON exports |
Development
npm install # install dev dependencies
npm run build # build TypeScript → dist/
npm test # build + run smoke tests
npm run check # tsc --noEmit
pm install . # load the built extension locally
Requirements
- pm-cli
>=2026.10.20 - Node.js
>=22.18.0
License
MIT
Release Automation
The repository release gate runs type checking, build, coverage, docstrings,
production dependency audit, package packing, and unbounded pm-changelog
validation. It also installs the real tarball into fresh npm/npx and Bun/bunx
projects on the pinned 2026.10.20 host and into npm/npx on the declared
2026.10.20 minimum, then executes both pm gantt and pm --quiet gantt export --format json against real tracker data. The daily workflow publishes at most
once when commits exist after the latest release tag. These technical gates do
not override repository-owned privacy or all-source coverage blockers.
Changelog scripts and the release workflow share scripts/pm-changelog.ts.
It retains the pinned generator's release selection and validation, then omits
only an empty leading Unreleased placeholder. Empty dated releases remain in
history, and pending work keeps its Unreleased section. Generation, stdout,
step summaries and strict byte comparisons all use the same rendered output.
Checks append a requested step summary even when the changelog is stale or
missing, while preserving their failure status and leaving the artifact untouched.
Output options use the pinned CLI parser: -o and --output accept split or
equals forms, and the last option selects the destination for generation and checks.
Multi-agent merge safety
This repo tracks its project management in .agents/pm/ and ships a committed .gitattributes
that maps those tracker artifacts to pm-cli's field-aware Git merge drivers, so concurrent-branch
tracker edits merge cleanly instead of hard-conflicting. The driver definitions live in
per-clone Git config; npm install / npm ci wires them automatically via the prepare script, scripts/prepare-merge-driver.ts: the launcher template pm-ops ships, copied unchanged, which a test compares byte for byte with the pinned template. It runs pm-ops's installer, which calls pm merge install when the pm CLI is on PATH and skips with a notice when it is not. A production install of a clone (npm ci --omit=dev) has no pm-ops, so the launcher skips with one notice, while a stale or broken pm-ops fails the install. Registry installs of this package never run prepare. Being Node-based, it behaves identically on POSIX shells and Windows cmd.exe. To (re)run manually: npm run merge:install.
After merging a branch that touched .agents/pm/, reconcile any residual history-hash drift with
pm merge reconcile (pm-cli ≥ 2026.7.22): preview with pm merge reconcile --dry-run, apply with
pm merge reconcile --message "post-merge reconcile", then confirm with pm validate, which scans the
whole tracker and flags remaining history drift across every affected item (pm merge reconcile
itself lists each affected stream in its output; pm history --verify <id> spot-checks one item). The field-aware driver already unions every author's
content, so reconcile only re-greens the hash chain (no data loss) — see the authoritative
pm-cli merge-safety guide. The
older blunt pm history-repair --all remains available as a lower-level primitive.
Triplicate visual identity
Visual exports use build-time values from the exact pm-brand development pin:
form paper, carbon ink, ruled item sheets and explicit status fills. Portable font
stacks put Archivo, Public Sans and Martian Mono first and fetch no external fonts.
Design, themes, token parity and reproducible review renders.
The README banner embeds pm-brand's committed output at an immutable SHA.